Items to be checked before installation of cold storage ceiling cooling fan for large cold storage
1. After opening the outer package of the cold storage air cooler, check whether the components are loose, and tighten them again if they are loose;
2. Check whether the blades of the Cold storage air cooler axial flow air are firmly installed on the motor shaft, and whether the blades and the protective cover collide;
3. If the chiller is damaged or deformed due to transportation, it should be repaired before hoisting;
4. The chiller is pressurized by nitrogen and sealed by capillary before leaving the factory. Before installation, remove the sealing capillary tube. If there is a sound signal of air flow, the evaporation tube of the chiller is well sealed and can be used with confidence. If there is no airflow sound, it means that the evaporator tube is leaking, and it should be checked in installation;
5. D-type ceiling type chiller bolts are hoisted on the roof of the warehouse, and the hole distance is referred to the chiller instructions;
6. The distance between the ceiling type chiller and the wall (fan diameter 400mm or less than 400mm) should be kept 250-300mm, and the wind is conducive to the circulation of cold air in the cold storage and maintenance;
7. After installation, the suspended ceiling chiller should ensure the level;
8. The discharge pipe of the chiller leading to the cold storage should have a certain slope, so that the defrost water can be smoothly discharged out of the warehouse, and the connecting pipe outside the library should be U-shaped, and a certain liquid seal should be maintained in the pipe to prevent a large amount of hot air outside the library from entering the cold storage;
9. Heat insulation should be added outside the drain pipe in the cold storage, and electric heat pipes should be added inside the drain pipe when the temperature of the reservoir is lower than -20℃ to prevent the defrosting water from freezing during the drain process;
10. When installing the expansion valve, the temperature sensing bag must be tied tightly to the upper part of the horizontal return pipe and ensure good contact with the return pipe. The temperature sensing bag should be moisturized outside the return pipe to prevent the influence of the reservoir temperature;
11. The outlet of the chiller should avoid opening the beam or column, so as not to affect the air supply range;
12. The electrical wiring box of type D Freon suspended ceiling chiller is designed on the left side of the front of the chiller. The wiring box is divided into two types of low-power defrosting electric heat pipe terminals below 22㎡, and the second type of defrosting electric heat pipe terminals above 30㎡ adopt Y-type connection method. In addition, if one phase of the electric heat pipe is overheated and burned, it will not cause the other two phases of the electric heat pipe to overload;
13. When the defrosting electric tube is connected, the fan power supply must be disconnected to prevent the hot air blowing into the warehouse during defrosting;
14. The defrosting cycle is adjusted by the defrosting device to defrost 1-4 times per day and night, and the defrosting time is adjusted according to the thickness of the frost;
15. The defroster should have a delay function. When the defrosting ends, the chiller fan can not be started immediately to prevent the waste heat of the electric heating tube from blowing into the warehouse, which makes the temperature rise of the warehouse high and affects the items in the warehouse;
16 To check air cooler regularly, clean the fin dust, to ensure the cooling effect.